Microsoft project 2010 create resource pool free. Create and share a resource pool in Project desktop

Click OK and away you go. Was this information helpful?
Microsoft project 2010 create resource pool free.Establishing the resource pool
Upgrade to Microsoft Edge to take advantage of the latest features, security updates, and technical support. PWA helps you analyze your resource capacity to determine which projects can be delivered.
PWA will also help you identify where you have resourcing gaps. The resource analysis will provide a forecast of the additional cost required to deliver your target portfolio. This article will discuss how to configure your resource pool to correctly define the capacity in the resource analysis.
Resource analysis is a core feature in the Project Web Application, and is available in Project Online and supported versions of Project Server. The PWA Resource Center is where you populate the resources that will make up your available resource capacity. Your administrator is usually responsible for keeping this up to date.
Organizations generally define the resource pool using a combination of approaches:. Once the data has been imported, the administrator will need to add additional fields and values to correctly define resource capacity. Generic resources are placeholders with specific skills, such as Developer, Marketing Analyst, etc. These resources are often used in the project proposal process.
During this time, most organizations do not know which specific named resources will be performing the work. Generic resources do not count towards your organization’s capacity to deliver work. Named resources are specific resources that work within your organization. Named resources allow your organization to assign tasks to specific individuals. Named resources also support the calculation of available resource capacity in the resource analysis.
Assume your organization has a role of Marketing Analyst. That role is assigned to three projects, showing a requirement for three Marketing Analysts.
John and Jane are named resources. The resource analysis will determine a need for three Marketing Analysts, and compare this with the available capacity of two named resources. The resource analysis will conclude that only two projects may be performed. Many organizations define a standard list of roles. This list is defined as a resource-level custom field linked to a standard lookup table. Each role is then mapped to at least one generic resource and several named resources.
Make a note of the field you are using to assign standard roles. You will need this field name when you create the resource analysis. The resource pool represents the supply of available resources within the organization. The system administrator must configure the resource pool to support the portfolio analysis process. Following are key resource settings for consideration when configuring the enterprise resource pool:. The resource analysis will suggest the additional cost of hiring new resources to support the project portfolio.
This additional cost is calculated from the average standard rate of each resource assigned to the role. This cost is calculated as the average of John and Jane’s hourly rates. The resource pool has now been configured.
You are ready to define the resource demand. Skip to main content. This browser is no longer supported. Download Microsoft Edge More info. Table of contents Exit focus mode. Table of contents. In this article. The total resource availability in the Resource Analysis component is calculated as the total of the resource availability. Each resource should be assigned a specific role within Project Server.
The Portfolio Analysis module uses this field to calculate the total role availability and the average cost for a resource in that specific role.
This field must be created as an enterprise custom field and linked to a custom lookup table. The system utilizes the Standard Rate field to approximate the incremental costs of adding resources to a given portfolio.